Just finished the salon repairs today. Major milestone. And only a few things are left on the commissioning list, however one of them requires a haul out and there is a 6 week lead time for that. In the mean time we are ticking everything else off the list. Just lined up a few sea trials today for ABT stabilizers, main and wing engine application reviews (manufacturer sign off on the installations), a bunch of electronics tuning and adjustment, run out the whole anchor chain to confirm marking and length, and just some general exercise. Wired up my 30A 120V shore cord today and tested that to be sure it works as expected.