Anchor Locker Rebuild
After returning from our August 2019 vacation, we were talking about some things we could do to better organize the boat. One idea was to make better use of storage in the v-berth and the forward head. As part of that, we recognized that in our boat, there is some space in the v-berth bed cabinet that is wasted and inaccessible, and we started wondering about adding a drop-in storage compartment in there.
My son Josh started poking his head in the side compartments to see just how much space there was. He called out a couple minutes later to announce that all our chain was down in the bilge.
It turns out our anchor locker floor had collapsed. The plywood floor had delaminated and flexed until it let all the chain by.
Near as I can figure, the original builder had only ever installed a pull out plywood triangle piece of plywood, which would allow any saltwater/muck/whatever to drip/drain down into the bilge. Eventually, and likely during our tacking into the Strait of Georgia swells up off Patos Island, that old plywood finally gave way enough that our chain slid through down below.
It was Sunday. Next weekend was going to be Labor day – last long weekend of the summer. I had to work all week. Wednesday Josh hand pulled all the chain and laid it on deck.
Thursday I took all our fiberglass supplies and some likely candidate pieces of wood out to see if I could get something cobbled together.
It turns out when the chain collapsed, it pulled out anchor windlass cable out of its cable strap. It also turns out that our anchor locker bulkhead was nailed together, and those cables were up against the nails poking through.
I had the option of a quick temporary fix or doing it right the first time…sooooo I had this piece double ¾ exterior ply already laminated together, (to make 1 1/2 inches thick) and it was just about the right size. I cut another piece of ply to make a protective channel for the windlass cables and the washdown supply hose. And a third little block made a lower recess for my drain hole, down low.
Everything got 1.5 oz chopped strand mat on the bottom Thursday night. Friday, I got off work an hour early and headed out to the boat for a marathon work session. You miss it here because I didn't stop to take pictures but there was about two hours of grinding, sanding, vacuuming, itching, sweating, ugh. It was a tight area to work it, with the PPE I wear (This job was eye protection, respirator and ear protection.) I also didn't stop to take photos of the glass work - it was really warm and I had the resin kicking just right, and was OUT OUT OUT of gloves, so I didn't want to risk getting any on my cell. After some sanding/grinding in the anchor locker (all freshly ground glass, wiped clean and “moisturized” with acetone) and some more fitting, the pieces were in place and I was off to the races. Everything was installed first with thickened resin (cabosil and milled glass fibers) to make nice fillets and seal the edges, then tabbed first with 1.5 oz CSM then with multiple layers of 1708 biaxial cloth, followed up by an additional layer of CSM over everything, including the v-berth plywood wall, which had never been protected against moisture. After all that cured and got a quick sanding to deburr, it all got a nice coat of gelcoat to add to the waterproofing. The new anchor locker floor was installed sloped to the drain. I was done and on my way home to sleep at 0415 Saturday, and back up an out to the boat by late morning to start our long weekend.
Last but not least, a hole was drilled down and to aft out the side of the hull, and a clamshell vent added to the outside for the drain.
The anchor locker is now completely sealed. It will down out the side of the hull, about 18 inches above the water. It could potentially block up and fill with water. If it does, it will spill over the cable raceway down into the bilge before in comes into the v-berth.
Here's the final look, I didn't get any pics of the final drilled drail hole or clamshell vent - its a 1/2" hole with a SS clamshell, exactly how a Nordic Tug is fitted out.
Looking into the locker to starboard. The cable race is to protect the windlass cables and washdown hose. Out of sight and way up to the starboard is the windlass control relays.
Looking directly forward into the nose of the anchor locker from the v-berth.
Looking to port inside the anchor locker. The drain recess and the initial small pilot drill hole can be seen. The lowered recess was done to ensure that I could get a drain below the surface of the main anchor locker floor to make sure the bulk of all water would drain out of the locker.
Chain back in...
End result? ALL DONE. All of the plywood I added ended up completely encapsulated, and I added the waterproofing to the v-berth bulkhead that the chain sits up against. We went out to Hope IS for the weekend, anchored out, and what do you know, after we pulled in anchor we checked over the side and could see a little water draining out! whoot whoot!
Only issue is the current chain pipe is just a tad aft. If I ever add more than the 235 ft of chain I have, it will have to move forward or it will pile up into the access doors into the v-berth. All told this project took just over 1/2 gal of resin, 16 oz of gelcoat, and likely (I'm guessing) about 1/4 to 1/3 yard of 50" 1.5 oz CSM and 180" in of 9" 1708 seam tape. (I used up some 9" I had, then cut more from a roll of cloth I had.)